Bid Management · 8 min read

Two bids, the same quality and the same prices, can finish in a different order depending on a third bid that has no chance of winning. It sounds like a paradox. It is a mathematical property of some of the most common price scoring formulas in public procurement, and a bid team that does not read the formula before setting its price is pricing half blind.

Lesson 9.3, Commercial Proposal: Presenting Pricing and Terms Clearly, covers how to structure and itemise the price, set out the commercial terms, justify the price against the value and agree it across the company. This report is about the step before the presentation: understanding how the buyer will turn your price into points, what that means for the balance between price and quality, and how to test your price against the formula before you submit.

  • Relative or absoluteMost formulas score your price against the other bids. Some score it against a fixed reference.
  • The price of a pointEvery formula sets an exchange rate between euros and quality points. Calculate it.
  • SimulateTest your price against plausible competitor bids before you decide it.
  • A scene you may recognise
  • The commercial team spends a week cutting 4% from the price, convinced that price is worth 40% of the score. Nobody has worked out what 4% of price is worth in points under the buyer's formula. It turns out to be just over one point. The quality team, meanwhile, had identified two weaknesses in the technical answer that the reviewers expected to cost three or four points, and nobody had time to fix them.

The formulas you will meet

Directive 2014/24/EU requires contracting authorities to state the relative weighting of the award criteria, such as price 40% and quality 60% (Article 67(5)), but it does not prescribe how price is converted into points. The Court of Justice confirmed in Dimarso (C-6/15, 2016) that an authority need not always publish the evaluation method in advance, provided the method does not change the award criteria or their weighting. In practice, most tenders do publish a formula, and three families are common:

FormulaHow it worksWhat it rewards
Proportional to the lowest pricePoints = maximum points × lowest price ÷ your priceBeing close to the cheapest bid; your score depends on the lowest bid
Linear between lowest and highestThe lowest price gets full points, the highest gets zero, the rest in betweenYour position in the range; very sensitive to the highest and lowest bids
Against a reference pricePoints depend on your price compared with a budget or reference set in advanceYour own price; other bids do not change your score

The first two are relative: your score depends on the other bids. The third is absolute. The difference matters more than most bid teams realise.

How a losing bid can change the winner

Mats Bergman and Sofia Lundberg (2013), in a review of tender evaluation methods in public procurement, discuss a known weakness of combining weighted criteria with relative price scoring: rank reversal. The order between two bids can change when a third bid enters or leaves the competition, even though nothing about the first two has changed. Researchers in the field have argued that methods which allow this are hard to reconcile with the transparency the procurement rules require, and have recommended scoring price against a reference fixed in advance instead.

The effect is easy to demonstrate. In both examples below, quality is worth 60 points and price 40.

Linear scoring between lowest and highest price

Bids submittedBid A: €100k, quality 50Bid B: €110k, quality 59Winner
A and B only50 + 40 = 90.059 + 0 = 59.0A
A, B and C (€150k, quality 30)50 + 40 = 90.059 + 32 = 91.0B

With only two bids, B has the highest price and gets no price points at all. When an expensive, weak bid C arrives, B is no longer the most expensive, earns 32 price points and overtakes A. C never had a chance of winning; it decided the winner anyway.

Proportional scoring against the lowest price

Bids submittedBid A: €100k, quality 56Bid B: €110k, quality 59Winner
A and B only56 + 40.00 = 96.0059 + 36.36 = 95.36A
A, B and D (€80k, quality 35)56 + 32.00 = 88.0059 + 29.09 = 88.09B

Here a very cheap, low-quality bid D changes the reference for everyone. Price differences now count for fewer points, quality counts relatively more, and B overtakes A. The figures are illustrative and the margins are small on purpose: real evaluations are often decided by margins like these.

Calculate the price of a quality point

Every formula sets an exchange rate between euros and points. Knowing it turns a vague debate ("should we cut the price or improve the solution?") into a calculation.

  1. Estimate the likely lowest price. From market knowledge, previous awards and published contract values, estimate the range of the lowest bid.
  2. Calculate your price points at your intended price, and again at a price 1% lower.
  3. The difference is the value, in points, of 1% of your price. Under the proportional formula, if your price is 10% above the lowest bid and price is worth 40 points, cutting your price by 1% gains you only about 0.36 points.
  4. Compare it with quality. If your reviewers think a weak section is costing you three quality points, fixing it is worth as much as a price cut of roughly 8%, which few businesses can afford.

Simulate before you decide

A simple spreadsheet is enough. Put in the buyer's formula exactly as published, your expected quality score from the last review (see Score Yourself Before They Do, Module 7) and a few plausible competitor profiles: a cheap and basic bidder, a strong and expensive incumbent, a mid-market competitor. Then change one variable at a time.

  • Your price. At what price do you win against each profile? At what price do you stop winning whatever you do?
  • Your quality. How many quality points would you need to win at your current price?
  • A wild card. What happens if a very cheap or very expensive bidder enters? With relative formulas, test it.
  • The floor. Below which price would the bid be at risk of being considered abnormally low? Under Article 69, the authority must ask you to explain a price that appears abnormally low and may reject the tender if the explanation is not satisfactory.

The simulation does not tell you the competitors' prices. It tells you where your decision is sensitive and where it is not, which is what the approval board needs to know (Lesson 9.3, cross-functional sign-off).

What the formula means for the commercial proposal

  • Price exactly what is scored. If the formula uses the total price over four years, the evaluation will use that total. Make sure every element the buyer adds up is in your price schedule, in the required format and units.
  • Do not try to game the formula. Unbalanced prices, such as very low unit prices on items you expect to be little used, can be questioned as abnormally low or can make the tender non-compliant. Price honestly; use the simulation to decide, not to manipulate.
  • Explain the value where the rules allow it. The price schedule is scored by the formula; the value justification in the commercial narrative (Lesson 9.3) helps the evaluators and the approvers understand it.
  • Ask when the formula is unclear. If the tender does not say how price points are calculated, or the formula has an ambiguity, ask in the clarification period. The answer is shared with all bidders and protects everyone.

A 15-minute formula check

  1. Find the formula. Copy it exactly from the procurement documents, with the maximum points and the price element it uses.
  2. Classify it. Relative to the lowest price, linear between lowest and highest, or against a reference.
  3. Calculate the value of 1% of your price in points at your intended price and the likely lowest price.
  4. Compare with the quality gap. How many points do your reviewers think you are losing on quality, and what would it take to recover them?
  5. Test one wild card. If the formula is relative, add a very cheap and a very expensive imaginary bid and see whether your position changes.

A price simulation sheet

InputWhat to enter
FormulaThe buyer's formula, copied exactly, with the weights
Our quality scoreExpected score from the last internal review, with a low and a high estimate
Our priceIntended total, plus versions 2%, 5% and 10% lower
Competitor profilesThree to four plausible bidders, each with a price range and a quality estimate
Wild cardsA very cheap and a very expensive bid, for relative formulas
OutputsOur rank in each scenario; the value of 1% of price in points; the price at which we win; the abnormally low risk zone

Checklist

  • The price formula and weights are copied exactly from the tender.
  • The team knows whether the formula is relative or absolute.
  • The value of 1% of price in points has been calculated.
  • Price cuts and quality improvements have been compared in points.
  • The price has been simulated against plausible competitor profiles and wild cards.
  • The abnormally low risk zone has been considered.
  • The priced elements match exactly what the formula scores.
  • Unclear formulas were raised in the clarification period.

The weighting tells you how much price matters; the formula tells you how. Read it before you price, calculate what a percentage of price is worth in points, and simulate the competition you expect, including the bidders who cannot win but can still change the result. The best commercial decisions are made with the buyer's arithmetic in front of you.

Sources

3 sources

  1. Bergman, M. A., & Lundberg, S. (2013). Tender evaluation and supplier selection methods in public procurement. Journal of Purchasing and Supply Management, 19(2), 73–83.
  2. Court of Justice of the European Union, Case C-6/15, TNS Dimarso NV v Vlaams Gewest, judgment of 14 July 2016.
  3. Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement, Articles 67 and 69.eur-lex.europa.eu/eli/dir/2014/24/oj