Bid Managementpowered by Synaptix Log in

NewsReports

Score Alone, Then Talk

Bid Management · 6 min read

A Red Team brings together several experienced people to read the bid as evaluators will. Its value lies in the number of independent views: each reviewer notices different weaknesses. Yet many Red Teams begin with a discussion, often led by the most senior person in the room, and only then score. By the time the scores are written, the independent views have become one view, repeated several times. Research on group judgement explains why this happens, and public evaluators have a procedure designed to prevent it.

Lesson 11.1, The Multi-Stage Review Process, explains the colour team model and the value of diverse perspectives. This report adds the evidence on how social influence narrows those perspectives, the procedure EU evaluation panels use, and a Red Team format that keeps the reviewers' views independent until they are on paper.

  • IndependenceSeveral judgements are better than one only if they are formed separately.
  • Confidence risesDiscussion makes groups more confident, but not necessarily more accurate.
  • Write, then talkScore and comment alone, then discuss the differences.
  • An illustrative scenario
  • Six reviewers gather for the Red Team of a framework bid. The sales director opens by saying he likes the executive summary and finds the technical section "a bit long but solid". The discussion follows his lead. Two reviewers who had doubts about the implementation plan mention them briefly and drop them when nobody else picks them up. The scores, written at the end, cluster around 7 out of 10 for every section.
  • Two months later, the debrief shows the bid lost most points on the implementation plan: the evaluators found the timeline unrealistic and the risks unaddressed. Both reviewers who had doubts had noticed exactly that.
  • For the next bid, the team changes the format. Each reviewer scores every section alone, against the criteria, and writes down the reasons before the meeting. The meeting starts with a table of the scores, and the discussion goes first to the sections where the scores differ most.

What research says about group judgement

Social influence narrows the range

Jan Lorenz and colleagues (2011) asked groups of people to estimate quantities, such as the population density of Switzerland, over several rounds. Some participants saw nothing of the others' estimates; others saw the average or all the estimates of their group between rounds. Seeing the others' answers made the estimates converge, without making the group more accurate. It also made participants more confident. The authors called the loss of diversity, with no gain in accuracy, the undermining of the wisdom of crowds.

The pull of the group

Solomon Asch's classic experiments in the 1950s showed that many people will give an answer they can see is wrong, about the length of a line, when everyone else in the room gives it first. In a Red Team, the pressure is rarely so explicit, but the mechanism is the same: the first views expressed, especially by senior people, set the frame for those that follow. Irving Janis (1972) described the extreme form, groupthink, in which a cohesive group suppresses doubts to preserve agreement.

Decision hygiene

In Noise (2021), Daniel Kahneman, Olivier Sibony and Cass Sunstein recommend a simple remedy for professional judgements: obtain independent assessments before any discussion, then aggregate them. They call such practices decision hygiene, because, like washing hands, they prevent errors without needing to know in advance which ones would occur.

What the research does not show

These studies concern estimates and simple judgements, not the review of a 100-page proposal, and discussion has real value: a reviewer may explain a weakness the others missed. The point is not to avoid discussion but to order it. Independent scoring first preserves the diversity that makes a Red Team worth convening; discussion afterwards uses it.

How EU evaluators do it

The procedure described above is how many public evaluations already work. In Horizon Europe, the European Commission's research programme, each proposal is first assessed separately by several independent experts, each writing an individual evaluation report with scores and comments. Only then do the experts meet, usually with a moderator, to agree a consensus report. Many contracting authorities use a similar sequence for tenders: each member of the evaluation committee scores alone, then the committee meets to agree.

That has two consequences for bid teams. First, a Red Team that scores alone, then discusses, is simulating the evaluation more faithfully. Second, every evaluator reads the bid alone, so each section must make its case to a single reader, without anyone in the room to explain it.

A Red Team format that keeps views independent

  1. Send the bid and the scoring sheet in advance. With the evaluation criteria and weightings from the tender, and the scoring scale the buyer will use.
  2. Each reviewer scores alone. Every section, against each criterion, with a short reason for each score and the main strengths and weaknesses.
  3. Collect the sheets before the meeting. The bid manager combines them into one table: section by reviewer.
  4. Start the meeting with the table. No opening opinions. The senior people speak last on each section, not first.
  5. Discuss the differences first. Sections where scores differ by more than two points on a ten-point scale are discussed before those where everyone agrees.
  6. Agree actions, not a final score. The output is a list of changes with owners, not an average.

A worked example

A combined scoring table from the second Red Team in the scenario above, on a ten-point scale. The figures are illustrative.

Section (weight)Reviewer AReviewer BReviewer CSpread and action
Understanding of needs (15%)8781: no discussion needed
Technical solution (30%)8771: tighten length
Implementation plan (25%)8454: discuss first; B and C find the timeline unrealistic
Risk management (15%)7463: discuss second; risks not linked to the plan
Team and experience (15%)9881: no discussion needed

The table sends the discussion straight to the two sections that cost the earlier bid its points. In an open discussion led by the most enthusiastic reviewer, they might have been mentioned briefly and dropped.

An individual scoring sheet

FieldWhat the reviewer writes
Criterion and weightCopied from the tender, for example "2.3 Implementation plan (25%)"
ScoreOn the buyer's scale, with the buyer's definitions of each level
Main reasonOne sentence: why this score and not one higher
StrengthsWhat an evaluator would credit, with the page reference
WeaknessesWhat an evaluator would mark down, with the page reference
Change that would raise the scoreThe most important single change

A 15-minute test of your last Red Team

  1. Look at the scores. Were they written before or after the discussion?
  2. Look at the spread. If every reviewer gave almost the same score to every section, suspect that the views were not independent.
  3. Who spoke first? If it was the most senior person, the rest of the discussion probably followed.
  4. Compare with the debrief. Did the weaknesses the evaluators found appear in any reviewer's notes, even briefly?
  5. Count the actions. Did the review end with changes and owners, or with an overall impression?

Checklist

  • Reviewers receive the bid, the criteria and the scoring sheet in advance.
  • Each reviewer scores every section alone, with reasons, before the meeting.
  • The bid manager combines the scores into one table before the meeting.
  • The meeting starts with the table, not with opinions.
  • Senior reviewers speak last on each section.
  • The largest differences are discussed first.
  • The review ends with a list of changes and owners.

A Red Team of six people is worth six reviews only if six people form their views separately. Let each reviewer score alone, against the criteria, as each evaluator will. Then put the scores on the table and discuss where they differ. It costs no extra time, and it keeps the doubts that matter from being talked away.

Sources

5 sources

  1. Asch, S. E. (1956). Studies of independence and conformity: A minority of one against a unanimous majority. Psychological Monographs, 70(9), 1–70.
  2. European Commission. Horizon Europe Online Manual: proposal evaluation (individual evaluation and consensus).ec.europa.eu/info/funding-tenders/opportunities/docs/2021-2027/common/guidance/om_en.pdf
  3. Janis, I. L. (1972). Victims of Groupthink. Houghton Mifflin.
  4. Kahneman, D., Sibony, O., & Sunstein, C. R. (2021). Noise: A Flaw in Human Judgment. Little, Brown Spark.
  5. Lorenz, J., Rauhut, H., Schweitzer, F., & Helbing, D. (2011). How social influence can undermine the wisdom of crowd effect. Proceedings of the National Academy of Sciences, 108(22), 9020–9025.

More articles

All articles