Plan the Bid Backwards: The One-Third Rule

Bid Management · 11 min read

Most bid schedules fail in the same place. Not at the end, when everyone works late, but at the beginning, when the bid manager spends days reading, planning and preparing the kickoff, and the experts who write the answers receive their tasks with a fraction of the time they need. Military planners met this problem long before bid teams did, and they wrote a rule for it.

This report builds on Lesson 6.1, Developing a Realistic and Detailed Bid Schedule. The lesson gives the tools: the Work Breakdown Structure, three-point estimates, the critical path and time buffers. Here we look at how to use them in the order that protects the team's time: plan from the deadline backwards, keep your own planning short, estimate from past bids rather than from hope, and put the buffer where it actually protects the submission.

  • BackwardsStart from the submission deadline and the fixed points the buyer sets, then place every internal milestone before them.
  • One thirdUse at most a third of the available time for your own planning, and give the rest to the people who write, price and review.
  • Outside viewEstimate from what similar bids really took, and keep one shared buffer in front of the deadline.

Why bid schedules slip

Lesson 6.1 names the planning fallacy: we underestimate how long our own tasks will take, even when we know that similar tasks took longer in the past. The best-known study is by Roger Buehler, Dale Griffin and Michael Ross (1994). Psychology students predicted when they would finish their final-year thesis. On average they expected to need about 34 days; they needed about 55. Fewer than a third finished by the date they had predicted, and the average student took longer than their own worst-case estimate.

Two habits make this worse in bid teams. The first is that a task tends to fill the time it is given (Parkinson's law), so the slack built into one task is rarely passed on to the next. The second is what Eliyahu Goldratt called the student syndrome: when people know they have spare time, they start late, and the spare time is spent before the work begins.

The result is familiar. Each contributor adds a little safety to their own estimate, the safety disappears into late starts, and the delays add up along the critical path, while the time saved on early tasks is lost. By the final week, the reviews are squeezed, the executive summary is written last and the pricing is approved on the day of submission.

The one-third rule

The US Army's planning manual, FM 5-0 Planning and Orders Production (2024), gives commanders a simple guide for sharing time: use about one third of the time before execution for your own planning and orders, and leave the remaining two thirds to subordinate units for their own planning and preparation. The reasoning is that each level needs time of its own to turn the plan into action.

A bid has the same structure. The bid manager plans the response, and the people who write the technical solution, the method statements, the CVs and the price need their own time to plan and produce their part. The same rule applies one level down: a solution lead who receives eighteen days should not spend twelve of them before the writers start.

Use it as a ceiling, not a target

In a 35-day tender, a third would be almost twelve days. Very few bids can afford that much planning before the contributors start. The value of the rule is the ceiling it sets: if your own analysis, strategy and kickoff preparation are approaching a third of the time, you are spending the team's time, not yours. In practice, aim for the first three to five working days, and release work as soon as it is ready rather than all at once.

Warn early, then plan in parallel

FM 5-0 also describes the warning order: a short message sent as early as possible, with what is already known, so that subordinates can start preparing while the full plan is still being written. The bid equivalent costs one email and saves days.

  • Within a day of the Go decision, tell every likely contributor that the tender is coming, what it is about, when the kickoff will be and roughly how much of their time it will need.
  • Ask line managers to release the key subject matter experts (SMEs) for the dates you already know: the writing window, the reviews and the final week.
  • Send the parts of the tender each person can start on now: the CV template, the reference requirements, the pricing schedule, the mandatory forms.
  • Ask partners and subcontractors for the documents with long lead times: certificates, financial statements, signed declarations and letters of intent.

Parallel planning then lets each level start before the level above has finished. The bid manager refines the win strategy while the commercial lead builds the pricing model and the technical lead outlines the solution. The kickoff (Lesson 5.4) confirms and adjusts the work already started, instead of being the moment the work begins.

Plan from the deadline backwards

A schedule built forwards ("analysis takes three days, then writing takes ten") ends wherever the estimates add up to, and then gets compressed to fit. A schedule built backwards starts from the points that cannot move and leaves the compression visible from day one.

  1. Fix the external dates. The submission deadline, the last day for clarification questions, any site visit or bidder conference, and the validity period of the offer.
  2. Set the internal final deadline. The bid is complete, signed and ready to upload, at least one working day before the real deadline.
  3. Place the approvals. The final commercial and legal approval and the executive sign-off, with the dates agreed with the people who give them.
  4. Place the reviews. Work back from the approvals to the Red Team review, the time to correct after it, and the Pink Team review of the storyboards (Module 11).
  5. Allocate the remaining time to writing and pricing. Whatever is left between the kickoff and the first review belongs to the contributors. If it is not enough, you know on day two, not in the last week.
  6. Identify the critical path. As in Lesson 6.1, find the chain of dependent tasks that determines the end date: often pricing, which depends on the solution, which depends on the answers to clarification questions.

The fixed points in an EU public tender

The EU Public Procurement Directive (2014/24/EU) sets some of these dates for you, and the procurement documents set the rest. A few rules are worth building into every schedule:

  • Minimum time limits. In an open procedure, the minimum time for receipt of tenders is 35 days from the dispatch of the contract notice (Article 27). It can be shorter, for example 30 days when tenders are submitted electronically, or as little as 15 days after a qualifying prior information notice. Do not assume you will have more than the minimum.
  • Clarifications. Additional information requested in good time must be supplied to all tenderers no later than six days before the deadline (Article 53(2)); if it is not, the buyer has to extend the deadline (Article 47(3)). In practice, buyers set their own last date for questions, often well before that. Your questions are only useful if the answers arrive before the work that depends on them.
  • Answers are shared. Questions and answers are normally published to all tenderers. Plan time to read every answer as it arrives: it can change the scope, the format or the evaluation.
  • Electronic submission. Upload to the portal well before the deadline. Large files, digital signatures and portal problems take time, and a late upload is usually a rejected bid.

Estimate from the outside

Lesson 6.1 recommends three-point estimates (best case, most likely, worst case) and bottom-up estimates from the people who will do the work. Both help, but both are still forecasts made from the inside: the person imagines how this task will go. The Buehler study shows why that is not enough; even the worst-case estimates were too optimistic.

Daniel Kahneman and Amos Tversky proposed the remedy, and Bent Flyvbjerg turned it into a method for large projects: reference class forecasting. Instead of asking how long this task should take, ask how long similar tasks actually took, then adjust for what is really different this time. Flyvbjerg's work on infrastructure projects showed that this "outside view" corrects much of the optimism that inside estimates carry.

Build your own reference class

Most bid teams already have the data and do not use it. After each bid, record a few numbers in the lessons-learned log (Module 15):

Three or four bids are enough to see a pattern, for example that legal review always takes twice what was planned, or that pricing is always approved in the last two days. Those patterns are the most reliable inputs your schedule will ever have.

Put the buffer where it protects the bid

Lesson 6.1 asks for time buffers to absorb delays. Where you put them matters as much as how big they are. Goldratt's Critical Chain method (1997) suggests a different way to hold safety time: take the hidden margin out of individual tasks and put part of it into one shared buffer at the end of the critical chain, before the deadline.

For a bid, the shared buffer usually sits between the Red Team corrections and the final approvals. Track how fast it is being used, not only which tasks are late. A simple rule of thumb:

  • Green. The buffer is being used more slowly than the work is progressing. Carry on.
  • Amber. The buffer is being used at the same pace as the work. Look for the cause and plan a recovery.
  • Red. The buffer is being used faster than the work is progressing. Act now: reduce scope where the tender allows it, add people to the critical path or move an approval forward.

Two practical points make this work. Ask contributors to hand over as soon as their part is ready, rather than on the planned date, and make the buffer visible in the tracker (Lesson 6.5), so that the team sees the bid's real margin rather than its own.

When the deadline moves

Buyers extend deadlines, for example after late answers to clarification questions or a change to the documents. An extension is not new time for everyone's tasks. Keep the internal milestones, give the extra days to the critical path and the buffer, and tell the team which dates have changed and which have not.

When the time is shorter than the bid needs

Sometimes the backward schedule shows on day two that the work cannot fit, even with a tight plan. That is an input to the Go / No-Go decision (Module 2), not a reason to cut the reviews. Decide early what can be reused, what can be simplified within the rules of the tender and what extra people the critical path needs, or decide not to bid.

Checklist

  • The external dates are fixed first: deadline, last day for questions, site visits, offer validity.
  • The internal final deadline is at least one working day before the real one.
  • The early warning went out within a day of the Go decision.
  • Your own planning stays well under a third of the available time, and each level below applies the same rule.
  • Approvals and reviews are placed backwards from the deadline, with dates agreed by the people involved.
  • Estimates are checked against what similar bids actually took.
  • Clarification questions are sent early enough for the answers to be useful.
  • One shared buffer protects the submission, and its use is tracked.
  • The schedule is in the team's tracker, not only in the bid manager's head.

A backward schedule for a 35-day tender

The example below shows an open procedure with the minimum 35 days, counted back from the submission deadline (D). Adjust the proportions to the size of the bid and to your own reference class; the order is what matters.

WhenMilestoneWhat happens
Planning: the bid manager's time, kept short
D-35 to D-34Go decision and warningRead the documents, confirm the Go decision, send the early warning to contributors, partners and approvers.
D-33 to D-31Plan and kickoffCompliance matrix, win themes, the backward schedule and the RACI; kickoff on D-31 with work already started.
Production: the team's time, protected
D-31 to D-25Storyboards and questionsSection outlines, the clarification questions sent early, the pricing model and the partners' inputs.
D-24Pink Team reviewReview the storyboards against the evaluation criteria before full writing starts.
D-23 to D-13Writing and pricingFull drafts, graphics, CVs, references and the first full price.
D-12 to D-11Red Team reviewReview the complete draft as the evaluators will score it.
D-10 to D-7CorrectionsRewrite after the Red Team, finalise the price and the executive summary.
Protection: the shared buffer and the approvals
D-6 to D-4Shared bufferAbsorbs delays from the critical path. Unused, it becomes time for a final quality check.
D-3 to D-2Approvals and signaturesCommercial and legal approval, executive sign-off, signed declarations.
D-1Internal final deadlineUpload, confirmation of receipt, archive of the submitted version.
DSubmission deadlineKept free for problems that cannot be predicted.

Here the bid manager's own planning takes about four days, roughly a ninth of the time, well under the one-third ceiling. The contributors get more than three weeks to produce and correct, and the bid keeps a visible buffer and a free last day.

A schedule is a promise about other people's time. Plan it backwards from the deadline, keep your own share of it small, base it on what bids really take and protect it with one visible buffer. The team will spend its time on what wins, and the last day will be for checking, not for writing.

Sources

7 sources

  1. Buehler, R., Griffin, D., & Ross, M. (1994). Exploring the "planning fallacy": Why people underestimate their task completion times. Journal of Personality and Social Psychology, 67(3), 366–381.
  2. Directive 2014/24/EU of the European Parliament and of the Council of 26 February 2014 on public procurement, Articles 27, 47 and 53.eur-lex.europa.eu/eli/dir/2014/24/oj
  3. Flyvbjerg, B. (2006). From Nobel Prize to project management: Getting risks right. Project Management Journal, 37(3), 5–15.
  4. Goldratt, E. M. (1997). Critical Chain. North River Press.
  5. Kahneman, D., & Tversky, A. (1979). Intuitive prediction: Biases and corrective procedures. TIMS Studies in Management Science, 12, 313–327.
  6. Parkinson, C. N. (1955). Parkinson's law. The Economist, 19 November 1955.
  7. US Department of the Army (2024). FM 5-0: Planning and Orders Production.armypubs.army.mil