The Pre-Mortem: Imagine the Bid Has Already Failed

Bid Management · 7 min read

It is six weeks after submission. The letter from the contracting authority arrives, and the bid has failed. Take two minutes and write down why. Most bid teams can do this exercise in silence and produce a list that is sharper, more specific and more honest than anything in their risk register. That is the idea behind the pre-mortem.

Lesson 6.4, Risk Management Planning for the Bid Process, gives the framework: identify risks by category (operational, financial, relational and strategic), rate them by likelihood and impact, choose a response, record them in a risk register and monitor them through the bid. This report adds a technique for the step that is hardest to do well, the first one: finding the risks that really threaten this bid, early enough to act on them.

  • Imagine failureAssume the bid has already failed, and explain why. The question changes what people are willing to say.
  • Write first, talk laterEveryone writes their reasons alone before anyone speaks, so the first voice does not set the tone.
  • Owners and triggersThe best reasons go into the register, each with an owner, a response and a warning sign.

Why risk registers miss the risks that matter

Most bid risk registers look alike: key experts may not be available, the buyer may extend the deadline, the price may be too high. These risks are real, but they are generic, and they are written in a way that does not lead to any action. The risks that actually sink bids are usually more specific and more uncomfortable: the solution lead does not believe in the solution, the partner has not read the contract terms, the sales lead has a relationship with the buyer that is weaker than everyone assumes.

Those risks stay unspoken for good reasons. At a kickoff, the mood is optimistic; the Go decision has just been taken, and nobody wants to sound negative. Irving Janis, in his studies of policy fiascos, described how cohesive groups under pressure suppress doubts to preserve agreement, a pattern he called groupthink (1972). In a bid team, the most senior person in the room, often the Executive Sponsor or the sales lead who brought the opportunity, can make that pressure stronger without saying a word.

The technique

The psychologist Gary Klein described the pre-mortem in the Harvard Business Review in 2007. A post-mortem tells you why a project died, when it is too late to help. A pre-mortem moves it to the start: the team imagines that the project has already failed and works out what caused the failure.

Klein based the method on research by Deborah Mitchell, Jay Russo and Nancy Pennington (1989) on "prospective hindsight". When people imagine that an event has already happened, they find it easier to explain it; Klein reports that this increased people's ability to identify the correct reasons for future outcomes by about 30%. The change in question matters as much as the research. "What could go wrong?" invites caution and politeness. "It went wrong; why?" gives people permission to say what they already suspect.

Daniel Kahneman, who knew the risks of optimistic planning better than most, called the pre-mortem one of the most useful techniques he had come across, because it legitimises doubt in a group that has already committed to a decision (Thinking, Fast and Slow, 2011).

Running a pre-mortem for a bid

The best moment is soon after the kickoff, once the team knows the tender, the win strategy and the plan, but before the writing has absorbed everyone. For a large bid, a short second round before the Red Team review is worth it. Invite the core team, the key experts and, if possible, a partner representative. Forty-five minutes is enough.

  1. Set the scene (5 minutes). The bid manager summarises the opportunity, the win strategy and the plan in a few sentences, then states the failure: "the bid has failed".
  2. Write alone (5 minutes). Everyone writes their reasons in silence, on paper or in a shared document that is hidden until the end. Writing first prevents the first speaker from anchoring the discussion.
  3. Share in turns (15 minutes). Go round the room, one reason per person per round, until the lists are empty. The most senior person speaks last. No discussion yet, only clarifying questions.
  4. Group the reasons (5 minutes). Cluster them in the categories of Lesson 6.4: operational, financial, relational and strategic. Duplicates are a signal: if four people wrote the same reason, take it seriously.
  5. Choose the vital few (10 minutes). Rate the clusters by likelihood and impact, and pick the five to eight that matter most for this bid.
  6. Assign and close (5 minutes). For each chosen risk, name an owner and agree the first action. The detail goes into the risk register after the meeting.

Three failures, not one

Ask the team to imagine three different endings, because each one reveals different risks:

  • We were excluded. A missing document, an unsigned declaration, a late upload, a requirement not answered. These are compliance and process risks, and they are the cheapest to prevent.
  • We lost on the score. The buyer did not see our value, the competitor's solution looked stronger, the price was too high for the quality we offered. These are strategy and content risks.
  • We won, and regretted it. The contract terms transferred risks we could not carry, the price did not cover delivery, the partner could not perform. These are commercial risks, and they deserve the same attention as losing.

From the pre-mortem to the risk register

A pre-mortem is only useful if its results change the plan. Each risk chosen in the meeting becomes a row in the register described in Lesson 6.4, written so that someone can act on it.

For each risk, record the cause and the consequence, the likelihood and impact, the response chosen from the four Ts of Lesson 6.4 (tolerate, treat, transfer, terminate), the owner, the next action with a date, and the trigger: the observable sign that the risk is becoming real. Triggers turn monitoring into something concrete. "The architect has not sent the outline by Thursday" is a trigger; "the architect may be late" is not.

Keep it alive

Review the top risks in the weekly bid meeting, in five minutes, by checking the triggers rather than re-reading the whole register. Close the risks that have passed, add the ones that appear, and bring the list to the Red Team and to the final approval. After submission, compare the pre-mortem with what actually happened. It is one of the most useful inputs to the lessons learned (Module 15).

A pre-mortem sheet

Reason the bid failedCategory and ratingResponse, owner, trigger
Our technical drafts were late and the Red Team reviewed half a proposal.Operational. Likely, major.Treat: book the architect's blocks now, writer drafts from past bids. Owner: bid manager. Trigger: no outline by D-25.
The partner's CVs did not meet the mandatory experience criteria.Operational, compliance. Possible, catastrophic.Treat: check every CV against the criteria this week. Owner: bid coordinator. Trigger: any CV missing by D-20.
The buyer scored our method as generic.Strategic. Possible, major.Treat: Pink Team tests each section against the win themes. Owner: solution lead. Trigger: storyboard without client-specific evidence.
We won, but the liability cap made the contract unprofitable.Financial. Possible, major.Treat or transfer: legal review of the terms, clarification question, insurance quote. Owner: legal counsel. Trigger: no answer to the question by D-10.

What goes wrong with pre-mortems

  • It becomes a blame session. The failure is imaginary and belongs to the whole team. Reasons describe situations, not people: "the pricing was approved too late", not "Paul approved it too late".
  • The boss speaks first. If the Executive Sponsor opens with "I don't see any real risks", the exercise is over. Seniors speak last, or write like everyone else.
  • The risks stay vague. Push each reason until it names a cause and a consequence that someone could act on.
  • Nothing changes. A pre-mortem without owners, actions and triggers is an expensive way to feel worried. End the meeting with names and dates.
  • It comes too late. In the final week, the team can only list the risks it no longer has time to treat.

Checklist

  • The pre-mortem is scheduled soon after the kickoff, and again before the Red Team for large bids.
  • The question is framed as a failure that has already happened.
  • Everyone writes alone before anyone speaks; the most senior person speaks last.
  • The team imagines three endings: excluded, lost on the score, won and regretted.
  • Reasons are grouped in the categories of Lesson 6.4 and rated by likelihood and impact.
  • Every chosen risk has a cause, a consequence, a response, an owner, an action and a trigger.
  • Triggers are checked in the weekly bid meeting.
  • After submission, the pre-mortem is compared with what actually happened.

A risk register built in a hopeful kickoff lists the risks everyone is comfortable naming. A pre-mortem lists the ones they already suspect. Imagine the failure, let everyone write before anyone speaks, and turn the best reasons into owners, actions and triggers. The failure you imagined is the one you are most likely to prevent.

Sources

4 sources

  1. Janis, I. L. (1972). Victims of Groupthink. Houghton Mifflin.
  2. Kahneman, D. (2011). Thinking, Fast and Slow. Farrar, Straus and Giroux.
  3. Klein, G. (2007). Performing a project premortem. Harvard Business Review, 85(9), 18–19.hbr.org/2007/09/performing-a-project-premortem
  4. Mitchell, D. J., Russo, J. E., & Pennington, N. (1989). Back to the future: Temporal perspective in the explanation of events. Journal of Behavioral Decision Making, 2(1), 25–38.